A recurring question keeps popping up among the people who are working to build the new bridge between White Salmon and Hood River.
When will the crucial federal funding come?
Kathy Omer, part of Uplift Local’s team of Gorge Documenters, has heard this question for months at bridge authority meetings she’s attended. She wanted to learn what backup plan bridge officials have in mind, should federal funding come in late or less than expected.
So we spoke with Eric Wilson, who has served since July 2023 on the all-volunteer bridge authority — which runs the project — and recently became co-chair. He’s an architect by trade and has worked on large projects, but none as big as this.

—-
Uplift Local: Can you list all the different funding sources for the bridge and how much each brings in?
Eric Wilson: It’s kind of a three-legged stool in terms of funding. There’s the local — that will be covered by tolls. Each state, Oregon and Washington, have [put in] a big chunk of funding, $125 million each. The largest part is really the federal funding, and that is in a couple different flavors, so to speak.
The federal Bridge Investment Program is the biggest one. We are asking for $532 million for that grant, and we have two applications in, one for fiscal year ‘25 and one for fiscal year ‘26. Normally [we] would have known something about [the first application] last spring or early summer. Instead, the current administration came out and asked applicants to reapply. So we went ahead and did two applications, and we’re waiting to hear on both of those. We would only receive one.
Uplift Local: Aren’t we already in federal fiscal year 2026?
Wilson: Yes.
Uplift Local: So they asked people to resubmit applications for fiscal year 2025, but it would come out of fiscal year 2026 funding?
Wilson: It was part of what happened last spring, a lot of turmoil in the administrative transition, and that was how it was moved forward
Uplift Local: Do you want to walk us through the other federal funding too?
Wilson: So the other one is the INFRA grant, Infrastructure For Rebuilding America. And we received [approval of] that in January of ‘24. That is primarily a construction grant. We’re in the process of getting that [finalized] so we can start drawing on it.
Uplift Local: But you had worked out some kind of unusual agreement with the Federal Highway Administration that part of the money would be spent on design. And because of that, there is some concern the secretary of transportation might not sign off on it. What makes you worried that the secretary might not approve it with this split?
Wilson: I think that as we’ve come to learn more about the INFRA grant, it is really specifically a construction program. The good news is with the state funding, we have the money to do the design. You know, it’s you have to get the money to do the project, but you also have to get the money at the right time to keep the project moving, and the ability to flex, adjust and and deal with things in a slightly different way to make it keep moving, maintains that momentum.
Uplift Local: How did the idea of putting some design money into it come about?
Wilson: I really don’t know. I wasn’t involved in all of those discussions. I think at the time, I don’t know that we fully understood that it was only specifically for construction. And talking to the Federal Highway Administration they said, yeah, we could probably do this. You know, it’s one of those things everybody’s hearing what they want to hear, and you move forward.
Uplift Local: So what are the possible outcomes from the Department of Transportation with the INFRA grant?
Wilson: I think the possible outcome is that they don’t want to approve it in these two pieces and will just approve it in a single $200 million.
Uplift Local: When do you need the federal money to keep the bridge on schedule?
Wilson: Everything we are planning and working on right now is based on the assumption that we have full funding prior to 2027 and we can hit the in-water work window, which is October of 2027. That’s one big assumption based on half a dozen other minor, smaller assumptions. And the big question there is that BIP funding, We need to know that we’ve gotten that at some point. And you know, over the next six to 10 months, knowing that’s going to become increasingly important.
Uplift Local: So you need to know you’re going to get that BIP [Bridge Investment Program] funding some time over the next six to 10 months, and then you need the money by the in-water work window of 2027.
Wilson: Or the INFRA grant. Either one of those allows us to start, and the sooner you get agreement that we have been allocated something then we would be pushing hard to get some money sooner, so that we could take some risk items off the table, pre-buy material or anything like that.
Uplift Local: If either the INFRA grant or the BIP grant don’t come through, what happens?
Wilson: I don’t see any reason that the INFRA grant won’t come through. The BIP we have both applications in. They’re highly rated. We have strong support from our Oregon delegation in Washington D.C., our Washington delegation in Washington D.C., and also both states. So it’s hard for me to imagine that we wouldn’t get that. I think the more likely thing would be if we get half for ‘25 and we don’t know about half for ‘26. Then that kind of throws the calculus back up. What do we do? How do you react to that? It’s kind of a cliche, but that’s the secret sauce; how do you react when something different happens than you hope? There’s lots of little pieces, and there’s lots of options and at any given time, we’ve got four or five “what if” scenarios going on.
Uplift Local: Is there a chance this bridge will not get built?
Wilson: It needs to get built.
Uplift Local: How long is the new bridge supposed to be good for?
Wilson: Hoping 100 years.
Read full notes of the Feb. 23 Bi-Monthly Hood River-White Salmon Bridge Authority meeting by Documenter Kathy Omer.