The new bridge’s biggest need is money

by | Columbia Gorge, Meeting Note Summaries

August 26, 2026

Getting funding remains the top concern of the people trying to make a new Hood River-White Salmon bridge a reality. At the Aug. 24 Bridge Authority meeting, officials discussed tweaking a big federal grant application to try to move it from “recommended” to “highly recommended” status. Concerns with a key contractor means the Bridge Authority may seek other bidders for the big test pile project. Officials are also discussing bridge design concerns raised by Friends of the Gorge.

  • Update: In a special meeting Aug. 27, the Bridge Authority put policies in place to allow opening the test pile project to competitive bidding. 